BPA-G0747
400 MW hybrid in Klamath, OR · In queue since June 2022 · Proposed COD December 2026
400 MW
Capacity
2
Components
Solar + Battery
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
BPA-G0747 is a proposed 400 MW hybrid solar and battery project located in Klamath County, Oregon. The project consists of 200 MW of solar generation paired with 200 MW of battery energy storage. Interconnection is being requested through the Bonneville Power Administration (BPA) queue, with an entry date of June 1, 2022, and a proposed commercial operation date of December 1, 2026. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)".
The point of interconnection (POI) for the project is the BPA's LaPine-Chiloquin 230 kV line. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
BPA_x0019_s LaPine-Chiloquin 230 kV line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.