BPA-G0762
3 MW generation in Lake, OR · In queue since June 2022 · Proposed COD December 2024
3 MW
Capacity
1
Components
Solar
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 6m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
BPA-G0762 is a proposed solar generation project with a total capacity of 3 MW, located in Lake County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of June 28, 2022. The proposed commercial operation date is December 31, 2024.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the LaPine Substation.
Generated from interconnection queue and public data sources
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
LaPine Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0762