BPA-G0807
600 MW storage in Douglas, OR · In queue since September 2022 · Proposed COD December 2030
600 MW
Capacity
1
Components
Pumped Storage
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-10
The proposed project BPA-G0807 is a 600 MW pumped storage battery development in Douglas County, Oregon. The project is located in the West region and is listed in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of September 16, 2022. The proposed commercial operation date is December 10, 2030.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is at BPA's Gardiner 230 kV or Tahkenitch 230 kV Substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OR
County
Douglas
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
BPA's Gardiner 230 kV or Tahkenitch 230 kV Substation.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.