BPA-G0810
200 MW generation in Lane, OR · In queue since September 2022 · Proposed COD December 2030
200 MW
Capacity
1
Components
Biofuel
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-10
BPA-G0810 is a proposed 200 MW biofuel generation project located in Lane County, Oregon. The project is listed in the Bonneville Power Administration interconnection queue with an entry date of September 16, 2022, and a proposed commercial operation date of December 10, 2030. The interconnection agreement status is listed as "In Progress (unknown study)".
The point of interconnection (POI) is listed as Primary: Wendson 230 kV; Alternate: Takenitch 230 kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Lane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Primary: Wendson 230 kV; Alternate: Takenitch 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0810