BPA-G0818
3 MW generation in Wasco, OR · In queue since October 2022 · Proposed COD December 2025
3 MW
Capacity
1
Components
Solar
3y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
BPA-G0818 is a proposed solar generation project located in Wasco County, Oregon, with a total capacity of 3 MW. The project is listed in the Bonneville Power Administration interconnection queue, with an entry date of October 20, 2022, and a proposed commercial operation date of December 31, 2025. The point of interconnection is the Maupin-Tygh Valley #1 69 kV line.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
OR
County
Wasco
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Maupin-Tygh Valley #1 69 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0818