BPA-G0819
200 MW generation in Douglas, WA · In queue since November 2022 · Proposed COD December 2027
200 MW
Capacity
1
Components
Wind
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
BPA-G0819 is a proposed 200 MW wind generation project located in Douglas County, Washington. The project is listed in the Bonneville Power Administration interconnection queue with an entry date of November 2, 2022. The proposed commercial operation date is December 1, 2027.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Columbia-Grand Coulee No 1 230kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
WA
County
Douglas
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Columbia-Grand Coulee No 1 230kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0819