BPA-G0821
10 MW generation in Cassia, ID · In queue since November 2022 · Proposed COD December 2025
10 MW
Capacity
1
Components
Geothermal
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 1m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
BPA-G0821 is a proposed 10 MW geothermal generation project located in Cassia County, Idaho. The project, which entered the Bonneville Power Administration (BPA) interconnection queue on November 14, 2022, consists of a single 10 MW geothermal component. Its proposed commercial operation date is December 1, 2025.
The interconnection agreement for BPA-G0821 is currently listed as "In Progress (unknown study)" within the BPA queue. The point of interconnection is the BPA 138KV BRIDGE Substation. The project is listed as being developed by BPA.
Generated from interconnection queue and public data sources
State
ID
County
Cassia
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
BPA 138KV BRIDGE SUBSTATION
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.