BPA-G0839
300 MW hybrid in Jefferson, OR · In queue since February 2023 · Proposed COD December 2027
300 MW
Capacity
2
Components
Solar + Battery
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
BPA-G0839 is a proposed 300 MW hybrid solar and battery project located in Jefferson County, Oregon. The development project consists of 150 MW of solar generation paired with 150 MW of battery energy storage. It is listed in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of February 3, 2023, and a proposed commercial operation date of December 31, 2027.
The interconnection agreement (IA) status for BPA-G0839 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Jones Canyon-Santiam No 1 230kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Jones Canyon-Santiam No 1 230kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0839