BPA-G0841
600 MW hybrid in Lake, OR · In queue since February 2023 · Proposed COD December 2028
600 MW
Capacity
2
Components
Solar + Battery
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
BPA-G0841 is a proposed 600 MW hybrid Solar+Battery project located in Lake County, Oregon. The project consists of a 400 MW solar component and a 200 MW battery energy storage system. It is listed in the Bonneville Power Administration (BPA) interconnection queue with a queue entry date of February 15, 2023, and a proposed commercial operation date of December 1, 2028.
The interconnection request, under queue ID BPA-G0841, has an interconnection agreement (IA) status of "In Progress (unknown study)". The proposed point of interconnection (POI) is on the Grizzly-Summer Lake #1 or Grizzly-Captain Jack #1 500 kV lines.
Generated from interconnection queue and public data sources
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Grizzly-Summer Lake #1 or Grizzly-Captain Jack #1 500 kV lines.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.