BPA-G0849
800 MW hybrid in Sherman, OR · In queue since March 2023 · Proposed COD December 2027
800 MW
Capacity
2
Components
Solar + Battery
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
BPA-G0849 is a proposed 800 MW hybrid solar and battery project located in Sherman County, Oregon. The project, which consists of 400 MW of solar generation and 400 MW of battery energy storage, is in the Bonneville Power Administration (BPA) interconnection queue. The queue entry date is March 22, 2023, and the proposed commercial operation date is December 31, 2027.
The interconnection agreement (IA) status for BPA-G0849 is listed as "In Progress (unknown study)". The point of interconnection (POI) is primarily the Buckley-Grizzly No 1 500kV line, with a secondary POI at the Buckley Substation.
Generated from interconnection queue and public data sources
State
OR
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Primary: Buckley-Grizzly No 1 500kV line; Secondary: Buckley Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.