BPA-G0861
500 MW generation in Deschutes, OR · In queue since April 2023 · Proposed COD December 2027
500 MW
Capacity
1
Components
Wind
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
BPA-G0861 is a proposed 500 MW wind generation project located in Deschutes County, Oregon. The project is listed in the Bonneville Power Administration interconnection queue with an entry date of April 25, 2023. The proposed commercial operation date is December 31, 2027.
The interconnection agreement for BPA-G0861 is currently listed as "In Progress (unknown study)". The point of interconnection is the Grizzly-Summer Lake No 1 500kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OR
County
Deschutes
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Grizzly-Summer Lake No 1 500kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0861