BPA-G0862
400 MW storage in Sherman, OR · In queue since May 2023 · Proposed COD May 2027
400 MW
Capacity
1
Components
Battery
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-03
BPA-G0862 is a proposed 400 MW battery storage project located in Sherman County, Oregon. The project is listed in the Bonneville Power Administration interconnection queue with a queue entry date of May 11, 2023. The current proposed commercial operation date is May 3, 2027.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the John Day-Marion No 1 500kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
John Day-Marion No 1 500kV line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.