BPA-G0866
300 MW generation in Sherman, OR · In queue since June 2023 · Proposed COD September 2027
300 MW
Capacity
1
Components
Solar
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
The proposed BPA-G0866 project is a 300 MW solar generation facility located in Sherman County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of June 2, 2023, and a proposed commercial operation date of September 1, 2027. Its point of interconnection is the Buckley Substation.
The interconnection agreement (IA) for the project is currently listed as "In Progress (unknown study)". The developer is listed as BPA. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Buckley Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0866