BPA-G0871
500 MW generation in Lake, OR · In queue since June 2023 · Proposed COD December 2028
500 MW
Capacity
1
Components
Wind
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
BPA-G0871 is a proposed 500 MW wind generation project located in Lake County, Oregon. The project is listed in the Bonneville Power Administration (BPA) interconnection queue with an entry date of June 30, 2023. The proposed commercial operation date is December 1, 2028.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Captain Jack Substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Captain Jack Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0871