Project BPA-G0872 — Project Summary

Queue ID
BPA-G0872
Capacity
300 MW
Technology
Wind
Status
active
Location
Garfield, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BPA-G0872

BPA-G0872BetaActiveWindBPALBNL

300 MW generation in Garfield, WA · In queue since June 2023 · Proposed COD December 2028

300 MW

Capacity

1

Components

Wind

2y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection

Total Duration

5y 6m

In Study38%
Queue EntryJun 30, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

About

BPA-G0872 is a proposed wind generation project located in Garfield County, Washington, with a total capacity of 300 MW. The project is listed in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of June 30, 2023. The proposed commercial operation date is December 1, 2028. The interconnection agreement status is currently listed as "In Progress (unknown study)".

The development project consists solely of wind generation, with the full 300 MW capacity attributed to this technology. The point of interconnection (POI) is the Lower Granite Substation. The project has appeared in recent news coverage regarding renewable energy development in the Pacific Northwest.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

Garfield

Grid Region

Mountain West

Market

Developer

Utility

Bonneville Power Administration

Entity

BPA

Service Type

Point of Interconnection

Lower Granite Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.