BPA-G0872
300 MW generation in Garfield, WA · In queue since June 2023 · Proposed COD December 2028
300 MW
Capacity
1
Components
Wind
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
BPA-G0872 is a proposed wind generation project located in Garfield County, Washington, with a total capacity of 300 MW. The project is listed in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of June 30, 2023. The proposed commercial operation date is December 1, 2028. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The development project consists solely of wind generation, with the full 300 MW capacity attributed to this technology. The point of interconnection (POI) is the Lower Granite Substation. The project has appeared in recent news coverage regarding renewable energy development in the Pacific Northwest.
Generated from interconnection queue and public data sources
State
WA
County
Garfield
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Lower Granite Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0872