BPA-G0877
80 MW generation in Lane, OR · In queue since June 2023 · Proposed COD December 2029
80 MW
Capacity
1
Components
Biofuel
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-03
The proposed project BPA-G0877 is an 80 MW biofuel generation project located in Lane County, Oregon. Interconnecting to the Bonneville Power Administration (BPA) via the Albany-Lebanon No. 1 115kV line, the project entered the BPA interconnection queue on June 30, 2023, with a proposed commercial operation date of December 3, 2029. The interconnection agreement is currently listed as "In Progress (unknown study)".
The project consists of 80 MW of biofuel generation capacity. Recent news coverage indicates public interest in the development.
Generated from interconnection queue and public data sources
State
OR
County
Lane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Albany-Lebanon No. 1 115kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0877