BPA-G0879
80 MW generation in Lane, OR · In queue since June 2023 · Proposed COD December 2029
80 MW
Capacity
1
Components
Solar
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-03
The proposed BPA-G0879 project is an 80 MW solar generation project located in Lane County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with a queue entry date of June 30, 2023, and a proposed commercial operation date of December 3, 2029.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Lookout Point-Alvey No. 2 115kV line.
Generated from interconnection queue and public data sources
State
OR
County
Lane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Lookout Point-Alvey No. 2 115kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.