BPA-G0880
160 MW hybrid in Lane, OR · In queue since June 2023 · Proposed COD December 2030
160 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-02
BPA-G0880 is a proposed 160 MW hybrid solar and battery project located in Lane County, Oregon. The project consists of 80 MW of solar generation paired with 80 MW of battery storage. It is listed in the Bonneville Power Administration (BPA) interconnection queue with an entry date of June 30, 2023, and a proposed commercial operation date of December 2, 2030.
The interconnection agreement (IA) status for BPA-G0880 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Lookout Point-Alvey No. 2 115kV line.
Generated from interconnection queue and public data sources
State
OR
County
Lane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Lookout Point-Alvey No. 2 115kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0880