BPA-G0886
160 MW hybrid in Linn, OR · In queue since June 2023 · Proposed COD December 2030
160 MW
Capacity
2
Components
Biofuel + Battery
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-02
BPA-G0886 is a proposed 160 MW hybrid development project located in Linn County, Oregon. The project, which appeared in the Bonneville Power Administration (BPA) interconnection queue on June 30, 2023, consists of an 80 MW biofuel component and an 80 MW battery energy storage system. The proposed commercial operation date is December 2, 2030.
The project's interconnection to the BPA grid, at the Forest Grove-McMinnville No 1 115kV line, is currently listed as "In Progress" with an unknown study underway.
Generated from interconnection queue and public data sources
State
OR
County
Linn
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Forest Grove-McMinnville No 1 115kV line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0886