400 MW hybrid in Lane, OR · In queue since June 2023 · Proposed COD December 2030
400 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-02
BPA-G0890 is a proposed 400 MW hybrid Solar+Battery project in Lane County, Oregon. The project consists of 200 MW of solar generation and a 200 MW battery energy storage system. It is located in the Bonneville Power Administration (BPA) service area and interconnects at the Lane Substation at 230 kV.
The project is currently active in the BPA interconnection queue, with a queue entry date of June 30, 2023, and a proposed commercial operation date of December 2, 2030. The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Lane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Lane Substation at 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.