BPA-G0891
400 MW hybrid in Lane, OR · In queue since June 2023 · Proposed COD December 2030
400 MW
Capacity
2
Components
Solar + Battery
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-02
BPA-G0891 is a proposed 400 MW hybrid Solar+Battery project located in Lane County, Oregon. The project, consisting of 200 MW of solar generation and 200 MW of battery energy storage, is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of June 30, 2023. The proposed commercial operation date is December 2, 2030.
The interconnection agreement (IA) for BPA-G0891 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Lane Substation at 230 kV. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
OR
County
Lane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Lane Substation at 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.