BPA-G0904
400 MW hybrid in Linn, OR · In queue since June 2023 · Proposed COD December 2030
400 MW
Capacity
2
Components
Biofuel + Battery
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-01
BPA-G0904 is a proposed 400 MW hybrid project located in Linn County, Oregon. The project, which combines biofuel and battery technologies, is being developed within the Bonneville Power Administration (BPA) region. It consists of a 200 MW biofuel component and a 200 MW battery component.
The project is currently active in the BPA interconnection queue, having entered the queue on June 30, 2023, with a proposed commercial operation date of December 1, 2030. The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Santiam-Chemawa No 1 230kV line.
Generated from interconnection queue and public data sources
State
OR
County
Linn
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Santiam-Chemawa No 1 230kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.