BPA-G0918
300 MW generation in Lane, OR · In queue since August 2023 · Proposed COD October 2029
300 MW
Capacity
1
Components
Wind
2y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-10-31
The proposed BPA-G0918 project is a 300 MW wind generation facility located in Lane County, Oregon. The project is listed in the Bonneville Power Administration (BPA) interconnection queue with an entry date of August 24, 2023. The proposed commercial operation date is October 31, 2029.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Santiam-Alvey 1&2 No 1 230kV line. The project has appeared in recent news coverage regarding renewable energy development in the Pacific Northwest.
Generated from interconnection queue and public data sources
State
OR
County
Lane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Santiam-Alvey 1&2 No 1 230kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0918