BPA-G0935
225 MW generation in Walla Walla, WA · In queue since September 2023 · Proposed COD September 2027
225 MW
Capacity
1
Components
Solar
2y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-15
The proposed project BPA-G0935 is a 225 MW solar generation project located in Walla Walla County, Washington. The project was entered into the Bonneville Power Administration (BPA) interconnection queue on September 13, 2023, with a proposed commercial operation date of September 15, 2027. The point of interconnection is the Central Ferry-Lower Monumental No 1 500 kV Line.
The interconnection agreement for project BPA-G0935 is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
WA
County
Walla Walla
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Central Ferry-Lower Monumental No 1 500 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0935