BPA-G0944
261 MW generation in Morrow, OR · In queue since October 2023 · Proposed COD September 2026
261 MW
Capacity
1
Components
Solar
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
BPA-G0944 is a proposed solar generation project with a total capacity of 261 MW, located in Morrow County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of October 3, 2023, and a proposed commercial operation date of September 1, 2026. The point of interconnection is the Six Mile Substation, with a secondary point on the Boardman-Alkali No 1 115kV line.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The project is being managed within the BPA queue.
Generated from interconnection queue and public data sources
State
OR
County
Morrow
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Six Mile Substation; Secondary: Boardman-Alkali No 1 115kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.