BPA-G0945
202 MW hybrid in Fremont, ID · In queue since October 2023 · Proposed COD June 2026
202 MW
Capacity
2
Components
Solar + Battery
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
BPA-G0945 is a proposed 202 MW hybrid solar and battery project located in Fremont County, Idaho. The development project, which consists of 150 MW of solar capacity and 52 MW of battery storage, is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of October 4, 2023. The proposed commercial operation date is June 1, 2026.
The interconnection agreement (IA) for BPA-G0945 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Goshen-Drummond No 1 161kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
ID
County
Fremont
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Goshen-Drummond No 1 161kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0945