BPA-G0953
600 MW generation in Lincoln, WA · In queue since October 2023 · Proposed COD September 2026
600 MW
Capacity
1
Components
Wind
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
BPA-G0953 is a proposed 600 MW wind generation project in Lincoln County, Washington. The development project is located in the West region and is being managed through the Bonneville Power Administration (BPA) interconnection queue. The project entered the queue on October 5, 2023, with a proposed commercial operation date of September 1, 2026.
The interconnection agreement for BPA-G0953 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is yet to be determined.
Generated from interconnection queue and public data sources
State
WA
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
TBD
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0953