BPA-G0957
10 MW generation in Benton, WA · In queue since October 2023 · Proposed COD July 2027
10 MW
Capacity
1
Components
Solar
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
The proposed BPA-G0957 project is a 10 MW solar generation facility located in Benton County, Washington. The project is listed in the Bonneville Power Administration interconnection queue with an entry date of October 6, 2023. The developer is currently unknown.
The proposed commercial operation date is July 1, 2027. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Benton-White Bluffs No 1 line or White Bluffs-Richland No 1 line.
Generated from interconnection queue and public data sources
State
WA
County
Benton
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Benton-White Bluffs No 1 line or White Bluffs-Richland No 1 line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0957