BPA-G0958
400 MW generation in Wasco, OR · In queue since October 2023 · Proposed COD June 2027
400 MW
Capacity
1
Components
Wind
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
The proposed BPA-G0958 project is a 400 MW wind generation facility located in Wasco County, Oregon. The project is listed in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of October 6, 2023. The proposed commercial operation date is June 1, 2027. The point of interconnection is the John Day - Marion No 1 500kV line.
The interconnection agreement (IA) status for the BPA-G0958 project is currently "In Progress (unknown study)". The project consists of 400 MW of wind generation capacity. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
OR
County
Wasco
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
John Day - Marion No 1 500kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0958