BPA-G0961
650 MW storage in Umatilla, OR · In queue since October 2023 · Proposed COD December 2028
650 MW
Capacity
1
Components
Battery
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
BPA-G0961 is a proposed battery storage project with a total capacity of 650 MW. The project is located in Umatilla County, Oregon, and is being managed within the Bonneville Power Administration (BPA) interconnection queue. The project entered the queue on October 11, 2023, with a proposed commercial operation date of December 1, 2028.
The interconnection agreement (IA) for BPA-G0961 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) for the project is the McNary Substation at 230 kV.
Generated from interconnection queue and public data sources
State
OR
County
Umatilla
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
McNary Substation at 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.