BPA-G0963
650 MW storage in Morrow, OR · In queue since October 2023 · Proposed COD December 2030
650 MW
Capacity
1
Components
Battery
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-02
BPA-G0963 is a proposed 650 MW battery storage project located in Morrow County, Oregon. The project, under development within the Bonneville Power Administration (BPA) service area, entered the BPA interconnection queue on October 11, 2023. The proposed commercial operation date is December 2, 2030.
The interconnection agreement (IA) for BPA-G0963 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Longhorn Substation at 230 kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Morrow
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Longhorn Substation at 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.