BPA-G0971
160 MW hybrid in Lane, OR · In queue since October 2023 · Proposed COD December 2028
160 MW
Capacity
2
Components
Biofuel + Battery
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The proposed project BPA-G0971 is a 160 MW hybrid development project located in Lane County, Oregon. The project, which combines Biofuel and Battery technologies, consists of an 80 MW Biofuel component and an 80 MW Battery component. It is listed in the Bonneville Power Administration (BPA) interconnection queue with an entry date of October 13, 2023, and a proposed commercial operation date of December 1, 2028.
The interconnection agreement (IA) for project BPA-G0971 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Eugene-Alderwood No 1 115kV line.
Generated from interconnection queue and public data sources
State
OR
County
Lane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Eugene-Alderwood No 1 115kV line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0971