BPA-G0973
300 MW generation in Mason, WA · In queue since October 2023 · Proposed COD December 2029
300 MW
Capacity
1
Components
Wind
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
BPA-G0973 is a proposed wind generation project with a total capacity of 300 MW. The project is located in Mason County, Washington, and is being managed within the Bonneville Power Administration (BPA) interconnection queue. The queue entry date is October 14, 2023, with a proposed commercial operation date of December 1, 2029.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Olympia-Shelton No 3 230kV line. The project has appeared in recent news coverage regarding renewable energy development in the Pacific Northwest.
Generated from interconnection queue and public data sources
State
WA
County
Mason
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Olympia-Shelton No 3 230kV line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.