BPA-G0974
250 MW generation in Wasco, OR · In queue since October 2023 · Proposed COD December 2029
250 MW
Capacity
1
Components
Wind
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
BPA-G0974 is a proposed wind generation project located in Wasco County, Oregon, with a total capacity of 250 MW. The project is listed in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of October 14, 2023, and a proposed commercial operation date of December 1, 2029. The point of interconnection is the Parkdale Substation.
The interconnection agreement for BPA-G0974 is currently listed as "In Progress (unknown study)". The project consists of 250 MW of wind generation capacity. The project has appeared in recent news coverage regarding renewable energy development in the Pacific Northwest.
Generated from interconnection queue and public data sources
State
OR
County
Wasco
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Parkdale Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0974