Project BPA-G0981 — Project Summary

Queue ID
BPA-G0981
Capacity
300 MW
Technology
Wind
Status
active
Location
Sherman, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BPA-G0981

BPA-G0981BetaActiveWindBPALBNL

300 MW generation in Sherman, OR · In queue since November 2023 · Proposed COD September 2028

300 MW

Capacity

1

Components

Wind

2y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection

Total Duration

4y 10m

In Study38%
Queue EntryNov 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-01

About

BPA-G0981 is a proposed 300 MW wind generation project located in Sherman County, Oregon. The project is listed in the Bonneville Power Administration interconnection queue, with an entry date of November 3, 2023. The proposed commercial operation date is September 1, 2028. The point of interconnection is the John Day Substation at 500 kV.

The interconnection agreement for the project is currently listed as "In Progress (unknown study)". There has been recent news coverage of the project.

Generated from interconnection queue and public data sources

Project Details

State

OR

County

Sherman

Grid Region

Mountain West

Market

Developer

Utility

Bonneville Power Administration

Entity

BPA

Service Type

Point of Interconnection

John Day Substation at 500 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project BPA-G0981