BPA-G0986
300 MW hybrid in Skagit, WA · In queue since November 2023 · Proposed COD December 2029
300 MW
Capacity
2
Components
Wind + Battery
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-30
BPA-G0986 is a proposed 300 MW hybrid wind and battery project located in Skagit County, Washington. The project consists of 150 MW of wind generation and 150 MW of battery energy storage. It is listed in the Bonneville Power Administration (BPA) interconnection queue with an entry date of November 3, 2023, and a proposed commercial operation date of December 30, 2029.
The interconnection agreement (IA) status for BPA-G0986 is listed as "In Progress (unknown study)". The point of interconnection (POI) is primarily the Sedro-Woolley - Bellingham No 1 230kV line, with a secondary POI at the Murray - Custer No 1 230kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
WA
County
Skagit
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Primary: Sedro-Woolley - Bellingham No 1 230kV line; Secondary: Murray - Custer No 1 230kV line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0986