BPA-G0988
200 MW generation in Spokane, WA · In queue since November 2023 · Proposed COD September 2028
200 MW
Capacity
1
Components
Wind
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
BPA-G0988 is a proposed 200 MW wind generation project located in Spokane County, Washington. The project is listed in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of November 6, 2023. The proposed commercial operation date is September 1, 2028.
The interconnection agreement for BPA-G0988 is currently listed as "In Progress (unknown study)". The point of interconnection is the Grand Coulee-Bell No 6 500 kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
WA
County
Spokane
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Grand Coulee-Bell No 6 500 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0988