Project BPA-G0991 — Project Summary

Queue ID
BPA-G0991
Capacity
200 MW
Technology
Wind
Status
active
Location
Curry, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BPA-G0991

BPA-G0991BetaActiveWindBPALBNL

200 MW generation in Curry, OR · In queue since November 2023 · Proposed COD September 2028

200 MW

Capacity

1

Components

Wind

2y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection

Total Duration

4y 10m

In Study38%
Queue EntryNov 6, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-01

About

BPA-G0991 is a proposed 200 MW wind generation project located in Curry County, Oregon. The project is listed in the Bonneville Power Administration interconnection queue with an entry date of November 6, 2023. The proposed commercial operation date is September 1, 2028.

The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Fairview-Rouge No 1 230 kV line.

Generated from interconnection queue and public data sources

Project Details

State

OR

County

Curry

Grid Region

Mountain West

Market

Developer

Utility

Bonneville Power Administration

Entity

BPA

Service Type

Point of Interconnection

Fairview-Rouge No 1 230 kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project BPA-G0991