BPA-G0996
400 MW generation in Douglas, OR · In queue since November 2023 · Proposed COD December 2029
400 MW
Capacity
1
Components
Solar
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
BPA-G0996 is a proposed solar generation project located in Douglas County, Oregon, with a total capacity of 400 MW. The project consists of 400 MW of solar photovoltaic generation. It is listed in the Bonneville Power Administration interconnection queue with an entry date of November 6, 2023, and a proposed commercial operation date of December 1, 2029. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Grand Coulee-Schultz No 1 500kV line.
Generated from interconnection queue and public data sources
State
OR
County
Douglas
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Grand Coulee-Schultz No 1 500kV line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G0996