BPA-G1003
3 MW generation in Adams, WA · In queue since November 2023 · Proposed COD December 2025
3 MW
Capacity
1
Components
Solar
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 1m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
The proposed project BPA-G1003 is a 3 MW solar generation project located in Adams County, Washington. Interconnecting to the Bonneville Power Administration (BPA) grid, the project entered the BPA interconnection queue on November 16, 2023, with a proposed commercial operation date of December 31, 2025.
The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Hatton tap to Connell tap to Benton-Scooteney No 1 115kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
WA
County
Adams
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Hatton tap to Connell tap to Benton-Scooteney No 1 115kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.