BPA-G1007
600 MW hybrid in Lewis, WA · In queue since November 2023 · Proposed COD October 2030
600 MW
Capacity
2
Components
Wind + Battery
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-10-30
BPA-G1007 is a proposed 600 MW hybrid wind and battery project located in Lewis County, Washington. The project, which consists of 300 MW of wind generation and 300 MW of battery storage, is in the Bonneville Power Administration interconnection queue as of November 17, 2023. The proposed commercial operation date is October 30, 2030.
The interconnection agreement for BPA-G1007 is currently listed as "In Progress" with an unknown study. The point of interconnection is the Paul Substation.
Generated from interconnection queue and public data sources
State
WA
County
Lewis
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Paul Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G1007