BPA-G1013
250.1 MW generation in Umatilla, OR · In queue since November 2023 · Proposed COD December 2030
250.1 MW
Capacity
1
Components
Wind
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-31
BPA-G1013 is a proposed wind generation project located in Umatilla County, Oregon, with a total capacity of 250.1 MW. The project is being developed within the Bonneville Power Administration (BPA) utility territory. It entered the BPA interconnection queue on November 21, 2023, with a proposed commercial operation date of December 31, 2030.
The interconnection agreement (IA) for BPA-G1013 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Combine Hills II tap to Walla Walla-Pendleton No 1 69 kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OR
County
Umatilla
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Combine Hills II tap to Walla Walla-Pendleton No 1 69 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G1013