BPA-G1016
400 MW generation in Klickitat, WA · In queue since November 2023 · Proposed COD December 2029
400 MW
Capacity
1
Components
Solar
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
BPA-G1016 is a proposed solar generation project located in Klickitat County, Washington, with a total capacity of 400 MW. The project is in the Bonneville Power Administration interconnection queue, with an entry date of November 21, 2023, and a proposed commercial operation date of December 31, 2029. The interconnection agreement status is listed as "In Progress (unknown study)".
The project consists of 400 MW of solar photovoltaic generation. The point of interconnection is the Wautoma-Knight No 1 500kV line.
Generated from interconnection queue and public data sources
State
WA
County
Klickitat
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Wautoma-Knight No 1 500kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.