BPA-G1023
1,023.6 MW hybrid in Lake, OR · In queue since November 2023 · Proposed COD June 2030
1,023.6 MW
Capacity
2
Components
Solar + Battery
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
BPA-G1023 is a proposed hybrid solar and battery project located in Lake County, Oregon, with a total capacity of 1023.6 MW. The project, which appeared in recent news coverage, consists of a 508.5 MW solar component and a 515.1 MW battery component.
The development project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of November 21, 2023, and a proposed commercial operation date of June 1, 2030. The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Ponderosa Substation.
Generated from interconnection queue and public data sources
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Ponderosa Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.