BPA-G1024
1,023.6 MW hybrid in Lake, OR · In queue since November 2023 · Proposed COD November 2030
1,023.6 MW
Capacity
2
Components
Solar + Battery
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
7 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-11-15
BPA-G1024 is a proposed 1023.6 MW hybrid solar and battery project located in Lake County, Oregon. The project consists of a 508.5 MW solar component and a 515.1 MW battery component. It is listed in the Bonneville Power Administration (BPA) interconnection queue with an entry date of November 21, 2023, and a proposed commercial operation date of November 15, 2030. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Ponderosa Substation.
The development project is located in the West region. It is currently listed as an active project in the interconnection queue.
Generated from interconnection queue and public data sources
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Ponderosa Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.