BPA-G1030
300 MW hybrid in Grant, WA · In queue since November 2023 · Proposed COD December 2028
300 MW
Capacity
2
Components
Solar + Battery
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-29
BPA-G1030 is a proposed 300 MW hybrid solar and battery project located in Grant County, Washington. The project, which consists of 200 MW of solar generation and 100 MW of battery storage, is in the Bonneville Power Administration (BPA) interconnection queue as of November 21, 2023. The proposed commercial operation date is December 29, 2028.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Rocky Ford-Grand Coulee No 1 230kV line. The project is listed as active within the interconnection queue.
Generated from interconnection queue and public data sources
State
WA
County
Grant
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Rocky Ford-Grand Coulee No 1 230kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.