Project BPA-G1031 — Project Summary

Queue ID
BPA-G1031
Capacity
250 MW
Technology
Solar
Status
active
Location
Klickitat, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BPA-G1031

BPA-G1031BetaActiveSolarBPALBNL

250 MW generation in Klickitat, WA · In queue since November 2023 · Proposed COD May 2028

250 MW

Capacity

1

Components

Solar

2y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection

Total Duration

4y 6m

In Study38%
Queue EntryNov 21, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-02

About

BPA-G1031 is a proposed solar generation project located in Klickitat County, Washington, with a total capacity of 250 MW. The project is listed in the Bonneville Power Administration interconnection queue, with an entry date of November 21, 2023, and a proposed commercial operation date of May 2, 2028.

The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the McNary-Ross No 1 345 kV line.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

Klickitat

Grid Region

Mountain West

Market

Developer

Utility

Bonneville Power Administration

Entity

BPA

Service Type

Point of Interconnection

McNary-Ross No 1 345 kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project BPA-G1031