Project BPA-G1032 — Project Summary

Queue ID
BPA-G1032
Capacity
500 MW
Technology
Solar
Status
active
Location
Grant, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BPA-G1032

BPA-G1032BetaActiveSolarBPALBNL

500 MW generation in Grant, WA · In queue since November 2023 · Proposed COD October 2028

500 MW

Capacity

1

Components

Solar

2y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection

Total Duration

4y 11m

In Study38%
Queue EntryNov 21, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-31

About

BPA-G1032 is a proposed 500 MW solar generation project located in Grant County, Washington. The project, under development within the Bonneville Power Administration (BPA) interconnection queue, entered the queue on November 21, 2023, with a proposed commercial operation date of October 31, 2028. The point of interconnection is the Grand Coulee-Hanford No 1 500 kV line.

The interconnection agreement status is currently listed as "In Progress (unknown study)". The project has appeared in recent news.

Generated from interconnection queue and public data sources

Project Details

State

WA

County

Grant

Grid Region

Mountain West

Market

Developer

Utility

Bonneville Power Administration

Entity

BPA

Service Type

Point of Interconnection

Grand Coulee-Hanford No 1 500 kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.