BPA-G1041
750 MW hybrid in Sherman, OR · In queue since November 2023 · Proposed COD January 2027
750 MW
Capacity
2
Components
Wind + Battery
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-06
BPA-G1041 is a proposed 750 MW hybrid wind and battery project located in Sherman County, Oregon. The development project consists of a 500 MW wind farm coupled with a 250 MW battery energy storage system. It is listed in the Bonneville Power Administration (BPA) interconnection queue, having entered the queue on November 21, 2023, with a proposed commercial operation date of January 6, 2027.
The interconnection agreement (IA) for BPA-G1041 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Ashe-Marion No 2 500 kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OR
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Ashe-Marion No 2 500 kV line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G1041