300 MW storage in Sherman, OR · In queue since November 2023 · Proposed COD January 2027
300 MW
Capacity
1
Components
Battery
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-06
BPA-G1042 is a proposed 300 MW battery storage project located in Sherman County, Oregon. The project is listed in the Bonneville Power Administration interconnection queue, with an entry date of November 21, 2023. Its proposed commercial operation date is January 6, 2027. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Ashe-Marion No 2 500 kV line.
The development project consists solely of battery storage, with a total capacity of 300 MW. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
OR
County
Sherman
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Ashe-Marion No 2 500 kV line.
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G1042